Development projects in Barkarbystaden

Barkarbystaden is Järfälla's major urban development area: the old airfield and southern Veddesta are to hold 14,000 homes and 30,000 new residents by 2035, with the metro's blue line reaching Barkarbystaden and Barkarby – planned for December 2027, but since Region Stockholm's review in September 2026 expected in the fourth quarter of 2028; no new timetable has been decided.

The facts are read from Järfälla municipality's and Trafikverket's own pages, and every section shows when it was last checked.

New homes
14,000

When does the metro open in Barkarbystaden?

The opening is planned for December 2027, but since Region Stockholm's review in September 2026 expected in the fourth quarter of 2028 – no new timetable has been decided. Region Stockholm's metro expansion administration presented the review of every metro project on 25 September 2026, and it expects the blue line to Barkarby to open about a year later than planned. The explanation given for the programme as a whole is that the work is taking longer than expected: delays in the rock excavation have carried over into the contracts that follow, several ongoing contracts are progressing slowly, and the time needed to test the system before opening was underestimated. The project and station pages on nyatunnelbanan.se still say December 2027. The same review puts the line's cost at 9.9 billion kronor in current prices, against 7.4 billion in agreed funding.

The blue line is extended about four kilometres from Akalla to two new stations, Barkarbystaden and Barkarby, and the journey to T-Centralen will take 24 and 26 minutes respectively. The line was originally to open in 2026; a dispute with a contractor in 2023 cost around a year and a half, and re-planning then recovered part of it. Even on the new estimate, it remains the first of the new metro lines to open.

The build has moved on to fit-out and installations, and all concrete work is finished at both stations. In March 2026 the project notified the Land and Environment Court that the construction period affecting groundwater was over, and by the end of that month the escalators were in place and installed in both of Barkarbystaden's entrances. In June the first rails went down at Barkarbystaden station, and by September the track was complete on the stretch where both tracks share one tunnel – track-laying now continues in the two separate tunnels towards Akalla.

The rest of the interchange at Barkarby station comes first. The station house's north entrance to the commuter trains opened on 28 March 2026, and the new bus terminal of around 6,000 square metres is planned to open in December 2026, as the platforms for regional and long-distance trains enter service, according to Trafikverket. From 13 December SJ regional trains will stop at Barkarby on most departures between Stockholm Central and Västerås, Örebro and Gothenburg – it is in Trafikverket's 2027 timetable, the municipality announced on 22 September 2026.

Source: Nya tunnelbanan – Barkarby · Nya tunnelbanan 2026-06-30 · Nya tunnelbanan 2026-03-03 · Trafikverket – Barkarby · Byggindustrin · Nya tunnelbanan 2026-09-25 · Nya tunnelbanan 2026-09-22 · Nya tunnelbanan 2026-03-31 · Nya tunnelbanan – station Barkarbystaden · Nya tunnelbanan – arbeten i Barkarbystaden · Nya tunnelbanan – arbeten i Veddesta · Barkarby.se 2026-09-22 · read 2026-09-26

Under way and coming

Individual buildings with a published timetable. The links go to the city's own project pages.

Tunnelbanestation Barkarbystaden

Infrastructure · Sveatorget / Flygfältsplatsen
Region Stockholm

The blue line's new station 30–35 metres down, with two entrances along Barkarbyvägen: at Sveatorget and at Flygfältsplatsen. The concrete work is finished, the escalators have been in place in both entrances since March 2026, the first track on the Barkarby branch was in place in June, and by September track-laying was complete on the stretch where both tracks share one tunnel; Barkarbystaden to T-Centralen will take 24 minutes. The station page still says December 2027, but Region Stockholm's review of 25 September 2026 expects the opening to slip by about a year, to the fourth quarter of 2028 – no new timetable has been decided yet.

In other districts:The same blue line is getting a station in Slakthusområdet

Opening planned for December 2027; now expected in Q4 2028● Under construction

Tunnelbanestation Barkarby

Infrastructure · Veddestabron / Veddestavägen
Region Stockholm

The line's terminus 30 metres down: the north entrance inside the new station house at Veddestabron, the south one by Veddestavägen and the new street Banmästargatan. The concrete work is finished and the station is being fitted out – by September 2026 the escalators down to the platform were installed. Barkarby to T-Centralen will take 26 minutes. The opening is planned for December 2027, but since Region Stockholm's review of 25 September 2026 it is expected in the fourth quarter of 2028 – no new timetable has been decided.

Opening planned for December 2027; now expected in Q4 2028● Under construction

Barkarby bussterminal och regionaltågsplattformar

Infrastructure · Barkarby station
Region Stockholm and Trafikverket

A new bus terminal of around 6,000 square metres and 355-metre platforms for regional and long-distance trains at Barkarby station, in the 4,000-square-metre station house whose north entrance opened on 28 March 2026. The tracks are planned to open for train traffic when the terminal is finished in December 2026, according to Trafikverket. Trafikverket's 2027 timetable has SJ regional trains stopping at Barkarby from 13 December 2026 – most departures between Stockholm Central and Västerås, Örebro and Gothenburg, the municipality announced on 22 September 2026.

Planned to open December 2026 – regional trains from 13 December● Under construction

Å-rummet, förlängning söderut

Park · Bällstaån, Vagnsgatan–Barkarbybron
Järfälla municipality

The park corridor along Bällstaån is being extended south from Vagnsgatan to Barkarbybron. Work began in August 2026 according to the municipality's barkarby.se, and through the autumn the ground is being excavated and reinforced, with most transport kept inside the site, according to the municipality's development page. Further south the park gives way to meadow, birch woodland and a wetland that takes the water in heavy flows; the first stage of Å-rummet opened in May 2024.

Complete spring 2029● Under construction

Kvarter 7 och 9 – lokaler vid tunnelbanan

Offices · Vid tunnelbaneuppgången
Åke Sundvall

10,500 square metres of commercial space for offices, restaurants, services and retail in the two blocks by the metro entrance that Åke Sundvall signed a development agreement for with the municipality on 11 May 2026. Block 9, with the metro entrance inside the building, is under way – Åke Sundvall announced the ground-breaking on 3 September 2026 – and holds 8,000 square metres: services, shops, restaurants and cafés at street level and two floors for offices, care and health in a podium beneath three towers designed by BAU. Block 7 is planned to start in 2027; the homes in both blocks are on the Housing page.

Block 9 under way since 2026, block 7 planned for 2027● Under construction

Veddestavägen och cykelstråket längs Bäckparksgatan

Infrastructure · Veddesta
Järfälla municipality

The municipality is finishing the stretch of Veddestavägen in front of the new bus terminal, with work planned to run until December 2026, and has started completing the new regional walking and cycling route along Bäckparksgatan, which is to continue along Norrviksvägen and link the Barkarby interchange to the City of Stockholm, according to the municipality's development page. Near Veddestabäcken it is also building a stormwater storage facility to take the load in cloudbursts, with work continuing until the new year according to the same page. The two new parks along Bäckparksgatan, one of them around a stormwater pond, are already open – the municipality announced their inauguration on barkarby.se on 9 September 2026.

Work planned until December 2026● Under construction

Flygfältsvägen, Hässlögatan och Predikantvägen

Infrastructure · Flygfältsvägen
Järfälla municipality

Flygfältsvägen is being made two-way during 2026 and gets a new walking and cycling path, speed bumps at the junctions and a new bus stop by Herrestaskolan; while it is closed, traffic runs on a temporary one-way road alongside it, from Herculesgatan to Barkarbyvägen. At the same time two new streets towards Kyrkbyn are being finished, Hässlögatan and Predikantvägen, with Predikantvägen extended from Kyrkbyn to meet Flygfältsvägen, according to the municipality's development page.

Complete in early 2027● Under construction

Högstadieskola (paviljong)

School · Vid Safirparken
Järfälla municipality

The district's first lower-secondary school: a pavilion school between Diagonalgatan, Jaktfalksgatan, Safirgatan and Flygfältsvägen, next to Safirparken, with room for 180 pupils in years 7–9 in the first stage and 270 when fully built. The decision to plan the school is dated 20 February 2026 in the municipality's timeline; the municipal executive board gave the go-ahead on 7 September 2026, with the final decision left to the municipal council's meeting of 21 September. Construction runs through winter and spring 2027 and the first pupils start in the autumn term of 2027 – a permanent F–9 school is planned for 2031, when the pavilion school closes.

Opens autumn term 2027○ Planned

Barkarby centrum (detaljplan)

Housing · Barkarby centrum
Järfälla municipality and Järfällahus

Around 740 homes, a stand-alone preschool and town-centre businesses at Barkarby centrum, partly on the site of today's bus terminal: five new blocks along Helikoptervägen with homes, shops, services and a mobility hub, plus five infill buildings along Flygarvägen and Jaktvägen, with squares and parkland that also handle stormwater and cloudbursts. The detailed plan was out for review 9 February–11 March 2026 and is being revised ahead of adoption, according to the municipality's planning page.

○ Planned

Already completed in Barkarbystaden

What already stands on the old airfield, with the year it opened: retail blocks, squares, schools, parks, the bridge and the station's new entrance. Several of them are in the directory.

Barkarby station, norra entrén — New entrance to the commuter trains in the coming station house at Veddestabron
Trafikverket, opened 28 March 2026 · completed 2026
Generalsparken — Park in the district's southern part
Järfälla municipality, opened 12 May 2026 · completed 2026
Safirparken — A 2,400-square-metre park by Lansengatan and Herculesgatan
Järfälla municipality, inaugurated 23 May 2026 · completed 2026
Parkerna vid Bäckparksgatan — Two parks in Veddesta – one around a stormwater pond with bridges, seating and a sun deck, and opposite it one with planting, hammocks, a water feature and insect hotels
Järfälla municipality, inauguration announced 9 September 2026 · completed 2026
Minnesparken — Memorial park on Ringvägen opposite Ålstaskolan, on the spot where a J34 Hawker Hunter crashed in 1957, with a flight memorial of three J34 aircraft
Järfälla municipality, inaugurated 28 March 2025 with the F8 and F18 veterans' associations · completed 2025
Å-rummet — Park corridor along Bällstaån
Järfälla municipality, first stage opened 28 May 2024 · completed 2024
Majorsparken — Park in the district's northern part, where Barkarbyvägen meets Ålsta allé, with trees, a pergola, play sculptures and sunken green areas that take the water in cloudbursts
Järfälla municipality, opening announced 6 September 2024 · completed 2024
Safirtorget — The district's newest square by Diagonalgatan
Järfälla municipality, opened gradually during October 2024 · completed 2024
Kvarter Atlas — Around 300 homes with Hemköp at street level, opposite Sveatorget
In the directory:Hemköp Barkarbystaden
Åke Sundvall and OBOS, inaugurated 28 November 2024 – the store opened 3 October · completed 2024
Ålstaskolan — Primary school F–5, in time F–6, Generalsgatan 4
Järfälla municipality, new building inaugurated 24 October 2023 · completed 2023
Bas Barkarby — Upper-secondary school, library, art gallery, culture school, sports hall and offices on 30,000 square metres
In the directory:Eatery Bas Barkarby
Atrium Ljungberg, opened January 2022 – library and gallery inaugurated 23 April 2022 · completed 2022
Veddestabron — 530-metre bridge over the railway between Barkarbystaden and Veddesta
Järfälla municipality, opened 21 June 2022 · completed 2022
Lidls huvudkontor — Lidl Sweden's 15,000-square-metre head office for 600 staff, BREEAM Excellent
In the directory:Lidl Barkarby
Lidl, inaugurated 12 April 2021 – the store next door opened 19 November 2020 · completed 2021
Herrestaskolan — Primary school F–6 for 300 pupils, built in solid timber
Järfälla municipality, opened 11 January 2016 · completed 2016
Stora torget — The district's western square by Flottiljen
Järfälla municipality, inaugurated 5 December 2015 · completed 2015
Flottiljens köpkvarter — Retail block with Maxi ICA, Systembolaget, a pharmacy and a drop-in clinic
ICA Fastigheter, opened 14 May 2014 – the airfield's first retail block · completed 2014
Kyrkparken — The district's city park – a multi-purpose park that doubles as a cloudburst park, with footpaths and places to meet
Opened June 2014, according to the municipality's timeline · completed 2014
Barkarby Gate — Retail block with sports, home and hobby stores, a gym and fast food
Barkarby Gate Fastigheter, opened 1 October 2014 · completed 2014

Source: Järfälla municipality (barkarby.se)